Nixon Technology Center

Augusta, GA, United States

More data centers in Georgia →

Planned

Data being gathered. Capacity and impact data for this facility are not yet publicly available. We show what is known: name, operator, status, and location.

About this facility

3 G Investments filed rezoning, special-exception and DRI paperwork for the Nixon Technology Center, a proposed 3.34 million sq ft, seven-building data center campus on 383-388 acres near Augusta Regional Airport. It projects a 600 MW peak load and 2028/2029 go-live. The project remains unapproved; a hearing was postponed to Dec. 7, 2026, after a city data-center moratorium expired in September.

Last updated: November 4, 2026

Overview data not yet available

Capacity and location detail data for this facility are being gathered from public records. Check back as data becomes available.

Sources

Frequently asked questions

What is Nixon Technology Center?
3 G Investments filed rezoning, special-exception and DRI paperwork for the Nixon Technology Center, a proposed 3.34 million sq ft, seven-building data center campus on 383-388 acres near Augusta Regional Airport. It projects a 600 MW peak load and 2028/2029 go-live. The project remains unapproved; a hearing was postponed to Dec. 7, 2026, after a city data-center moratorium expired in September.
Where is Nixon Technology Center located?
Nixon Technology Center is located in Augusta, GA, United States.
Is Nixon Technology Center operational?
Nixon Technology Center is currently planned. Milestone dates are sourced from public planning records as they become available.

Data for Nixon Technology Center sourced from wrdw.com, augustachronicle.com, datacenterdynamics.com, wjbf.com. Values marked est. are estimates.